11th Ward 2015 Capital Plan

The 2015 Capital Plan Map is listed above. The streets highlighted in “red” indicate those that will be resurfaced as a part of CDOT’s arterial street resurfacing program. Please see below for a detailed description of each street:

Project: CDOT Arterial Street Resurfacing

Location: S Wentworth Ave, from Stevenson Expy/24th PL to Pershing/39th.

Status: In Progress. Scheduled to be completed by December 1st, 2015.

Work will include ADA sidewalk improvements, curb and gutter removal and replacement,

milling the existing asphalt pavement, asphalt paving, concrete bus pad construction, and

striping. Concrete work will be first followed by the milling and paving of the roadway.

During construction, temporary “No Parking” signs will be periodically installed as required for

each activity listed above. These temporary signs will restrict parking during work hours, while

adhering to rush hour restrictions, for the completion of the work.

 

Project: CDOT Arterial Street Resurfacing

Location: 35th Street, from Racine to Wentworth

Status: In Progress. Scheduled to be completed by December 1st, 2015.

Work will include ADA sidewalk improvements, curb and gutter removal and replacement,

milling the existing asphalt pavement, asphalt paving, concrete bus pad construction, and

striping. Concrete work will be first followed by the milling and paving of the roadway.

During construction, temporary “No Parking” signs will be periodically installed as required for

each activity listed above. These temporary signs will restrict parking during work hours, while

adhering to rush hour restrictions, for the completion of the work.

 

Project: CDOT Arterial Street Resurfacing

Location: Halsted St, from Archer to 31st.

Status: In Progress. Scheduled to be completed by December 1st, 2015.

Work will include ADA sidewalk improvements, curb and gutter removal and replacement,

milling the existing asphalt pavement, asphalt paving, concrete bus pad construction, and

striping. Concrete work will be first followed by the milling and paving of the roadway.

During construction, temporary “No Parking” signs will be periodically installed as required for

each activity listed above. These temporary signs will restrict parking during work hours, while

adhering to rush hour restrictions, for the completion of the work.