Capital Improvement Project Updates

Update on Street Resurfacing Projects going on in the 11th ward. The following streets are a part of Alderman Thompson’s 2015 Aldermanic Menu Program.

Canal, from 26th to 29th – Asphalt paving is complete.
33rd street, from Wells to Stewart – Asphalt paving is complete.
Union Ave, from 14th to 16th – Asphalt paving is complete.
Hillock Ave, from Stark ST to Throop ST – Asphalt paving is halfway complete. Work is currently in progress today.
37th ST, from Halsted to Lowe – Asphalt paving is complete.
Thank you to everyone for their patience as infrastructure construction continues throughout the City.